10.11 Given the following information, answer the questions about this project: Activity Expected Duration Predecessors A 4...
Question:
10.11 Given the following information, answer the questions about this project:
Activity Expected Duration Predecessors A 4 days —
B 9 days A C 11 days A D 5 days B E 3 days B F 7 days C G 3 days D, F H 2 days E, G I 1 day H