Question: 10.13 Develop a Gantt chart for the following activities. Identify all paths through the network. What is the critical path? Optional: Solve this problem with
10.13 Develop a Gantt chart for the following activities. Identify all paths through the network. What is the critical path?
Optional: Solve this problem with Microsoft Project. How does clicking on “Tracking Gantt” view demonstrate the critical path?
Activity Expected Duration Predecessors A 2 days —
B 3 days A C 4 days A D 4 days B, C E 5 days B F 6 days D G 4 days C, E, F Problems 377 378 Chapter 10