13.47 Your project is scheduled to last 3 months and cost $100,000. At the end of the...
Question:
13.47 Your project is scheduled to last 3 months and cost
$100,000. At the end of the first month, the project is 25%
complete. What is the Earned Value?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management Achieving Competitive Advantage
ISBN: 9780136057666
5th Edition
Authors: Jeffrey K. Pinto
Question Posted: