17. The following diagram was created before it was known that Mary would have to perform both...
Question:
17. The following diagram was created before it was known that Mary would have to perform both Activity B and Activity F.
a. With the realization that Mary has to do both tasks, indicate two possible critical chains.
b. Reschedule the work and show the position and the size of the feeding buffer.