24. The geographical location of the Largesse Hydro Project threatens it with weather-associated delays and costs. The
Question:
24. The geographical location of the Largesse Hydro Project threatens it with weather-associated delays and costs. The bad weather likelihood is estimated at 0.30, with a potential impact of delaying work by 10 weeks and increasing the cost by $20,000.
a. Ignoring the time and cost risks in Problem 23, what are the expected project completion time and completion cost considering the weather risk?
b. What is the estimated expected project completion time and cost considering the weather risk and the risks listed in Problem 23?