9. A small project consists of six tasks; the immediate predecessors and task durations are given in
Question:
9. A small project consists of six tasks; the immediate predecessors and task durations are given in the following table:
a. Draw an AON and an AOA precedence network for this project.
b. Using either network, find the following quantities: early and late starting times, early and late finishing times, total slack, free slack, safety slack, and independent slack.