Question: 9 Activity K cannot be loaded until completion of predecessors H, I, and J. K begins on February 6 and completes on February 12. Total
9 Activity K cannot be loaded until completion of predecessors H, I, and J. K begins on February 6 and completes on February 12. Total project delay = 3 days