A network-based schedule has four paths, namely 7, 8, 9, and 10 weeks. If the 10-week path

Question:

A network-based schedule has four paths, namely 7, 8, 9, and 10 weeks. If the 10-week path is compressed to 8 weeks, then:
A. We now have two critical paths.
B. The 9-week path is now the critical path.
C. Only the 7-week path has slack.
D. Not enough information is provided to make a determination.