A project has the following network and costs (T in days, C in $1,000s). a. What is

Question:

A project has the following network and costs (T in days, C in $1,000s).

image text in transcribed

a. What is the earliest the project can be completed under normal conditions? What is the direct cost?

b. What is the least costly way to reduce the project duration by 2 days? What is the project cost?

c. What is the earliest the project can be completed, and what is the least costly way of doing this? What is the project cost?