A project has the following network and costs (T in days, C in $1,000s). a. What is
Question:
A project has the following network and costs (T in days, C in $1,000s).
a. What is the earliest the project can be completed under normal conditions? What is the direct cost?
b. What is the least costly way to reduce the project duration by 2 days? What is the project cost?
c. What is the earliest the project can be completed, and what is the least costly way of doing this? What is the project cost?