A project has the following network and costs (T in days, C in $1,000s). a. Verify that
Question:
A project has the following network and costs (T in days, C in $1,000s).
a. Verify that the normal duration is 22 days and that the direct cost is $3,050.
b. What is the least costly way to reduce the project duration to 21 days? What is the project cost?
c. What is the least costly way to reduce the duration to 20 days? What is the project cost?
d. Now, what is the earliest the project can be completed, and what is the least costly way of doing this? What is the project cost?