Question: A white diamond on the tracking Gantt chart represents a slipped milestone. A slipped milestone refers to a milestone activity that was actually completed later
A white diamond on the tracking Gantt chart represents a slipped milestone. A slipped milestone refers to a milestone activity that was actually completed later than originally planned.