As a project manager, which of the following situations would concern you the most? a. a three-day
Question:
As a project manager, which of the following situations would concern you the most?
a. a three-day delay on an activity with five days total float
b. realizing that an activity on your critical path only took two days instead of the four you assigned it using the PERT method
c. a one-day delay to an activity with 0 total float
d. a two-day delay to a noncritical path activity with two predecessor activities
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Contemporary Project Management
ISBN: 9781337406451
4th Edition
Authors: Timothy Kloppenborg, Vittal S. Anantatmula, Kathryn Wells
Question Posted: