As a project manager, you establish a project policy that you, in advance of the meeting, review
Question:
As a project manager, you establish a project policy that you, in advance of the meeting, review all handouts presented to your external customer during project status review meetings. While reviewing the handouts, you notice that one slide contains company confidential information. Presenting this information to the customer would certainly enhance good will.
You should:
A. Present the information to the customer.
B. Remove the confidential information immediately.
C. Discuss the possible violation with senior management and the legal department before taking any action.
D. First discuss the situation with the team member that created the slide and then discuss the possible violation
with senior management and the legal department before taking any action.