Question:
Assume that the department manager has refused to see you again to discuss the new requirements. Time is running out, and you would like to make a decision before the costs and schedules get out of hand. From the list below, select your personal choice and then, after each group member is finished, find a group choice.
A. Disregard the new requirements, since they weren’t part of the original project plan.
B. Adhere to the new requirements, and absorb the increased costs and delays.
C. Ask the vice president and general manager to step in and make the final decision.
D. Ask the other department managers who may realize a schedule delay to try to convince this department manager to ease his request or even delay it.
Step by Step Answer:
Project Management A Systems Approach To Planning Scheduling And Controlling
ISBN: 9780471225775
8th Edition
Authors: Harold R. Kerzner