b. Refer back to Figure 10.24. Using the critical path from this activity network, consider A
Question:
b. Refer back to Figure 10.24. Using the critical path from this activity network, consider A – C – D – F – H as the critical path and assume all other paths are less than a fully crashed A – C – D – F – H. Prioritize the candidates for crashing. How does the activity network change the decision rule?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management Achieving Competitive Advantage
ISBN: 9780136057666
5th Edition
Authors: Jeffrey K. Pinto
Question Posted: