Do forward and backward pass calculations to indicate early and late start and finish times. Duration Predecessors
Question:
Do forward and backward pass calculations to indicate early and late start and finish times.
Transcribed Image Text:
Duration Predecessors (Months) C, E F. G ABCCGDGHE 2664341232 Activity Activity Description No. ABCDEFGHIK L Detailed site investigation and survey Detailed planning Detailed design Preparation of site Relocate services Re-align overhead track electrification Access road and ramp construction Piling Construct foundations and abutments Construct temporary supports to support bridge deck during construction Fabrication planning of structural steel components Manufacture structural steel components (off-site) 2 C 2 PO Q N erect on-site Erect pylons and fill with concrete Construct main span deck on pre-cast concrete beams Transport structural steel components and 1 M 23 J H, K, N, P R Install stay-cables and lift the bridge deck 3 Q off temporary supports STUVWXYNA Remove temporary supports 1 Electrical system installation 1 Roadway surfacing (paving) Finishing and ancillaries 2 2 Commissioning-cut-over 1 Formal handover and ceremony 1 Project sign-off 1 Z AA Administrative closure 1 RSST>x: T, U V W W Project end 0 (milestone) Y, Z
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 100% (QA)
Answered By
Bhartendu Goyal
Professional, Experienced, and Expert tutor who will provide speedy and to-the-point solutions. I have been teaching students for 5 years now in different subjects and it's truly been one of the most rewarding experiences of my life. I have also done one-to-one tutoring with 100+ students and help them achieve great subject knowledge. I have expertise in computer subjects like C++, C, Java, and Python programming and other computer Science related fields. Many of my student's parents message me that your lessons improved their children's grades and this is the best only thing you want as a tea...