During the Identify Risk Process, the project manager and the team categorize risks in an effort to
Question:
During the Identify Risk Process, the project manager and the team categorize risks in an effort to determine risks they may have missed. Of the following, which is the best example of risk categories?
a. Quality, schedule, budget
b. External, internal, technology, personnel
c. Scope, time, cost
d. Initiating, planning, executing, monitoring and controlling, closing