Given the following information regarding a project concerning an initial public offering (IPO),LO1 a. Draw the network.

Question:

Given the following information regarding a project concerning an initial public offering (IPO),LO1

image text in transcribed

a. Draw the network.

b. What is the critical path?

c. When will the offering be available (completion of the project)?

d. What is the effect on the project if activity e (approvals)
takes an extra week? Two extra weeks? Three extra weeks?