Given the schedule in Table B for a liability work package done as part of an accounting

Question:

Given the schedule in Table B for a liability work package done as part of an accounting audit in a corporation, find:LO1

a. The critical path.

b. The slack time on “process confirmations.”

c. The slack time on “test pension plan.”

d. The slack time on “verify debt restriction compliance.”

image text in transcribed