If a project manager is looking for revenue for a value-added scope change, the project manager's first

Question:

If a project manager is looking for revenue for a value-added scope change, the project manager's first choice would be:
A. Management reserve
B. Customer-funded scope change
C. Undistributed budget
D. Retained profits