If your sponsor asks for an estimate as to how much more money your team needs to
Question:
If your sponsor asks for an estimate as to how much more money your team needs to complete all project work as scheduled, which of the following formulas might you use?
a. BAC EAC
b. EV/PV
c. (BAC EV)/CPI
d. (BAC EV)/(EAC AC)