In Problem 15, suppose the likelihood of project success is 0.5 0.8 0.7 = 0.28.

Question:

In Problem 15, suppose the likelihood of project success is 0.5 × 0.8 × 0.7 = 0.28.

• What is the B/C ratio for the project?

• Which measure makes the project look more attractive, ECV or B/C? In your opinion, does the project merit approval?