Is the project really a success? What kind of follow-up steps should Finley and SLU have done

Question:

Is the project really a success? What kind of follow-up steps should Finley and SLU have done after the project was completed?

Construction of the new Information central building at South Land University (SLU) is completed on time and on budget. Administrators at SLU and managers at Finley Construction Company, the building’s prime contractor, are very pleased with the results. Besides meeting schedule and cost targets, the building and its equipment, including a variety of computer and technical gadgetry intended to augment learning, appear to have met all of the technical requirements. Much of the technology is leading edge, and some of it is being applied for the first time ever in a learning/
teaching environment by SLU. By all accounts, the project is a success.