One of your contractors has sent you an email requesting that they be allowed to conduct only

Question:

One of your contractors has sent you an email requesting that they be allowed to conduct only eight tests rather than the 10 tests required by the specification. What should the project manager do first?
A. Change the scope baseline.
B. Ask the contractor to put forth a change request.
C. Look at the penalty clauses in the contract.
D. Ask your sponsor for his or her opinion.