Project A is four months long, has four stakeholders, and has completed planning. Project B is 12 months long, has 10 stakeholders, and is in execution. Project C is 12 months long, has four stakeholders, and is in planning. Which project is most likely to experience scope creep?

a. Project A

b. Project B

c. Project C

d. Not enough Information