Reconsider Exercise 2, assuming a fixed overhead cost of $30 per day but no project deadline. What
Question:
Reconsider Exercise 2, assuming a fixed overhead cost of
$30 per day but no project deadline. What is the least-cost crash program? What if the overhead cost was $40? What if it was $60? LO9