The budgeted cost as of April 30 for a work package is $18,000. Suppose on April 30
Question:
The budgeted cost as of April 30 for a work package is $18,000. Suppose on April 30 the supervisor determines that only 80 percent of the scheduled work has been completed and the actual expense is $19,000. What is the BCWP? Compute SV, CV, SPI, and CPI for the work package.