The budgeted cost as of April 30 for a work package is $18,000. Suppose on April 30

Question:

The budgeted cost as of April 30 for a work package is $18,000. Suppose on April 30 the supervisor determines that only 80 percent of the scheduled work has been completed and the actual expense is $19,000. What is the BCWP? Compute SV, CV, SPI, and CPI for the work package.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: