The correct definition of resource leveling is: a. A graph that displays the resources used over time
Question:
The correct definition of resource leveling is:
a. A graph that displays the resources used over time on a project
b. The process of applying resources to a project’s activities
c. The process of creating a consistent (level) workload for the resources on the project, driven by resource constraints
d. A project schedule whose start and finish dates reflect expected resource availability