The following chart was prepared at the beginning of a HRM (Human Resource Management) crash hiring project.

Question:

The following chart was prepared at the beginning of a HRM (Human Resource Management) crash hiring project.

The project begins with two activities: Assemble interview team (A) and Budget resources (B).

LO1

image text in transcribed

The duration, in days, follows the letter of each activity.
What is the critical path? Which activities should be monitored most closely?
At the end of the first week, it was noted that activity A was completed in 2.5 days, but activity B required 4.5 days.
What impact does this have on the project? Are the same activities critical?