The project administrator is preparing a preliminary budget for a project and adds in the cost of

Question:

The project administrator is preparing a preliminary budget for a project and adds in the cost of a new computer for the project team to use. What type of cost would this computer purchase represent?

a. Variable

b. Direct

c. Indirect

d. Variable direct