Two project managers are looking for the same resource to perform work on their projects. In one
Question:
Two project managers are looking for the same resource to perform work on their projects. In one project, the work is on a task on a feeding path, in which the feeding buffer is 95 percent consumed. In the other project, the work is on the Critical Chain, in which the Critical Chain is 50 percent complete and the project buffer is 0 percent consumed. Which task should the resource be assigned to first? Why?