Use the activity specifications outlined in the table below to generate a first cut project schedule. From
Question:
Use the activity specifications outlined in the table below to generate a first cut project schedule.
From these specifications, develop a network schedule and answer the following questions.
a. What is the project duration?
b. What type of activity is 1.6?
c. What type of activity is 1.7?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management Theory And Practice
ISBN: 9780815360711
3rd Edition
Authors: Gary L. Richardson, Brad M. Jackson
Question Posted: