Use the following data to answer the questions that follow. Average velocity = (Remaining effort Day 1
Question:
Use the following data to answer the questions that follow.
Average velocity = (Remaining effort Day 1 - Remaining effort Current Day)/(Current Day 2 Day 1) Estimated completion date 5 Current Day 1 (Remaining effort/Average velocity)
a. Create a burndown chart for the given data using Excel or the software of your choice.
b. What is the average velocity for the project, in story points per day? (Assume the Current Day is Day 3).
c. What is the project’s expected completion date?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Question Posted: