Use the following information to answer parts a through h. Describe what the results of each calculation
Question:
Use the following information to answer parts a through h. Describe what the results of each calculation mean to you as a project manager. What do you propose to do?
PV $500,000 EV $350,000 AC $550,000 BAC $1,200,000
a. Schedule variance (SV)
b. Cost variance (CV)
c. Schedule performance index (SPI)
d. Cost performance index (CPI)
e. Estimate to complete (ETC—first method)
f. Estimate to complete (ETC—second method)
g. Estimate at completion (EAC)
h. To-complete performance index (TCPI)
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Contemporary Project Management
ISBN: 9781337406451
4th Edition
Authors: Timothy Kloppenborg, Vittal S. Anantatmula, Kathryn Wells
Question Posted: