Use the following information to answer parts a through h. Describe what the results of each calculation

Question:

Use the following information to answer parts a through h. Describe what the results of each calculation mean to you as a project manager. What do you propose to do?

PV $500,000 EV $350,000 AC $550,000 BAC $1,200,000

a. Schedule variance (SV)

b. Cost variance (CV)

c. Schedule performance index (SPI)

d. Cost performance index (CPI)

e. Estimate to complete (ETC—first method)

f. Estimate to complete (ETC—second method)

g. Estimate at completion (EAC)

h. To-complete performance index (TCPI)