Using the information in Problem 13.15, highlight the projects status on day 14 but assume that activity
Question:
Using the information in Problem 13.15, highlight the project’s status on day 14 but assume that activity D has not yet begun. What would the new tracking Gantt chart show? Print the output file.
Problem 13.15
Use the following information to construct a tracking Gantt chart using MS Project.
Highlight project status on day 14 using the tracking option and assuming that all tasks to date have been completed on time. Print the output file.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management Achieving Competitive Advantage
ISBN: 9781292269146
5th Global Edition
Authors: Jeffrey K.Pinto
Question Posted: