What should a project manager do if she encounters a flaw when evaluating the finished deliverables of

Question:

What should a project manager do if she encounters a flaw when evaluating the finished deliverables of a project?

A. Note the flaw and add it to a to-do list.

B. Reassign the project to another team member.

C. Address the flaw immediately to have it resolved.

D. Complete a Project Change Request form.