When the demand for resources is greater than the available supply, the project manager can use a
Question:
When the demand for resources is greater than the available supply, the project manager can use a scheduling method that adjusts the start and finish dates of activities in order to address resource limits or constraints. This technique is called ____________________ .
a. fast tracking
b. crashing
c. resource leveling
d. critical path method