When the demand for resources is greater than the available supply, the project manager can use a

Question:

When the demand for resources is greater than the available supply, the project manager can use a scheduling method that adjusts the start and finish dates of activities in order to address resource limits or constraints. This technique is called  ____________________ .

a. fast tracking

b. crashing

c. resource leveling

d. critical path method