Which of the following circumstances would require the creation of a lag relationship in a network diagram?

Question:

Which of the following circumstances would require the creation of a lag relationship in a network diagram?

a. The critical path

b. The insertion of a dummy variable into a network diagram

c. A delay after painting a room to allow for the paint to dry before beginning to carpet the room’s floor

d. An early finish relationship between two activities