You have been asked to price out a project for an outside customer. The project will run
Question:
You have been asked to price out a project for an outside customer. The project will run for eight months. Direct labor is $100,000 for each month and the overhead rate is fixed at 100 percent per month. Termination liability on the direct labor and overhead rate is 80 percent of the following month’s expenses. Material expenses are as follows:
Material A: Cost is $100,000 payable 30 days net. Material is needed at the end of the fifth month. Lead time is four months with termination liability expenses as follows:
30 days: 25%
60 days: 75%
90 days: 100%
Material B: Cost is $200,000, payable on delivery. Material is needed at the end of the seventh month. Lead time is three months with termination liability as follows:
30 days: 50%
60 days: 100%
Complete the table below, neglecting profits.
Step by Step Answer:
Project Management A Systems Approach To Planning Scheduling And Controlling
ISBN: 9780471741879
9th Edition
Authors: Harold Kerzner