3. Which of the following would be most likely to give rise to an exception report? (a)...

Question:

3. Which of the following would be most likely to give rise to an exception report?

(a) A new issue being raised

(b) A proposal to make a change to a deliverable

(c) The unexpected loss of a key team member

(d) Project tolerance being exceeded