3. Which of the following would be most likely to give rise to an exception report? (a)...
Question:
3. Which of the following would be most likely to give rise to an exception report?
(a) A new issue being raised
(b) A proposal to make a change to a deliverable
(c) The unexpected loss of a key team member
(d) Project tolerance being exceeded