3. Which of the lists below best identifies what is examined when a risk is assessed? (a)...
Question:
3. Which of the lists below best identifies what is examined when a risk is assessed?
(a) Probability, proximity, owner
(b) Impact, probability, team experience
(c) Cost, benefit, business case
(d) Probability, proximity, impact
Fantastic news! We've Found the answer you've been seeking!