1 Develop a budget for the project described in Table 11 assuming that the cost of each...
Question:
1 Develop a budget for the project described in Table 11 assuming that the cost of each activity is linearly distributed over its duration.
a. Assume an early-start schedule.
b. Assume a late-start schedule.
c. Assume that a “leveled budget” is desired (i.e., the same daily cost is desired for each day of the project).
TABLE 11 Duration Immediate Activity (days) predecessors Cost A 3 – $3,000 B 4 – $2,000 C 3 – $6,000 D 2 C $2,000 E 1 B $1,000 F 5 A $10,000 G 2 B $4,000 H 3 B $9,000 I 11 C $11,000 J 3 D, E $3,000 K 1 F,G $1,000 L 4 K $2,000 M 4 J,H $8,000
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management Processes Methodologies And Economics
ISBN: 9781292039404
1st Edition
Authors: Avraham Shtub
Question Posted: