4 Assume that a continuous timecost tradeoff exists for each activity, as shown in Fig. 3. Write...

Question:

4 Assume that a continuous time–cost tradeoff exists for each activity, as shown in Fig. 3.

Write out the corresponding linear program for minimizing the total project cost, defining all notation used.What constraint would you add to ensure that the project is completed within T time periods?