5 For the project data given in Table 13, assuming an overhead of $350 per period, find...

Question:

5 For the project data given in Table 13, assuming an overhead of $350 per period, find the minimum cost schedule.What are the critical activities? How much total slack and free slack exist for the noncritical activities? Find the cost of the early-start and late-start schedules. Re-solve the problem with a deadline of 9 weeks using the linear program developed in Exercise 4.