Each activity in a project can be performed by two different resource combinations (Table 4). Assume that

Question:

Each activity in a project can be performed by two different resource combinations (Table 4). Assume that the usage rate of each resource is constant throughout the duration of each activity. Now find a schedule that minimizes the time required to complete the project. Resources I and II both are available at a level of 12 hours each day.

TABLE 4 Immediate predecessors Mode 1 Duration (days) Resource I required (hours/activity) Resource II