A project is nearing completion, but a key activity is over budget. What should the project manager
Question:
A project is nearing completion, but a key activity is over budget.
What should the project manager do?
a) Ignore the budget overrun and continue with the project
b) Address the budget overrun by implementing corrective actions and updating the project budget
c) Update the project charter
d) Request additional funds