A project is nearing completion, but a key supplier is not meeting contract performance standards. What should
Question:
A project is nearing completion, but a key supplier is not meeting contract performance standards. What should the project manager do?
a) Ignore the supplier's performance and continue with the project
b) Address the performance issue by implementing corrective actions and updating the procurement management plan
c) Update the project charter
d) Request additional resources