A project manager discovers additional costs that were not included in the project budget. What should they

Question:

A project manager discovers additional costs that were not included in the project budget. What should they do?

a) Add the costs to the project budget immediately

b) Submit a change request for approval through the Perform Integrated Change Control process

c) Reject the additional costs to avoid budget changes

d) Update the project charter