A project manager discovers additional procurement requirements that were not included in the project plan. What should
Question:
A project manager discovers additional procurement requirements that were not included in the project plan. What should they do?
a) Add the requirements to the procurement management plan immediately
b) Submit a change request for approval through the Perform Integrated Change Control process
c) Reject the additional requirements to avoid changes
d) Update the project charter
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
PMP Exam Prep 2025 1000 Practice Questions And Answers With Explanation For The PMP Exam
ISBN: 9798227759948
1st Edition
Authors: Claire Georgette Wiman
Question Posted: