A project manager discovers additional stakeholder engagement requirements that were not included in the project plan. What should they do?
a) Add the requirements to the stakeholder engagement plan immediately
b) Submit a change request for approval through the Perform Integrated Change Control process
c) Reject the additional requirements to avoid changes
d) Update the project charter